The project scope included removing sections of an existing strip mall to create three new plazas with stone pavers and planters. New utility services were provided to these new spaces and all spaces received new rooftop units, lighting, and fire sprinklers. The exterior façade was built out with a combination of decorative steel elements, stone veneer, aluminum wall paneling, and stucco.
Immediately after award, MYC presented to the Owner and Architect a list of more than 20 items where we saw opportunities for cost savings. Many of these were pursued and substantial credit was provided to the Owner. MYC encouraged a cost-saving design strategy to build an exterior wall that allowed a bridal shop tenant to operate with as little disruption to their space as possible. Throughout the project, MYC served as a liaison for the Owner to tenants, the City, and utility companies.
Client:
W-PT Arvada VII, LLC
Location:
Arvada, Colorado